Hallelujah! Key section of Leith Walk to reopen on Monday

BUT TRAFFIC CHAOS IS FAR FROM OVER

Leith Walk will reopen to two-way traffic between Pilrig Street and London Road from Monday (18 July), marking a key milestone for the Trams to Newhaven project.

The main construction works between Montgomery Street/Annandale Street and Pilrig Street are now complete and fencing will be removed from outside businesses and homes.

The project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction anticipated to be complete by the end of 2022 ahead of a testing and commissioning period.

Progress to date includes:

  • Almost 3,900 metres of track laid, 84% of the total
  • Main construction works completed on three out of the eight new tram stops with works progressing well at the Balfour Street, Foot of the Walk and Newhaven stops
  • Over 4,000 metres of communications ducting installed (87% of the total) serving the tram and future communication requirements in the area
  • More than 4,000 metres of drainage installed (89% of the total)
  • Over 60,000 deliveries from the logistic hubs to local businesses
  • Almost 24,500 itison vouchers sold, generating over £240,000 potential spend in participating businesses on the route.
  • Over £175,000 spend on open for business campaigns
  • Main construction works complete on several sections, including Ocean Terminal to Rennie’s Isle and between Tower Street and Constitution Place and Tower Street and Baltic Street

However, the programme for some specific sections of the route has changed due to industry wide challenges with the availability of materials and skilled labour, as well as other issues including complex utility conflicts.

As a result, some stretches are scheduled to take longer than originally planned, including Melrose Drive and outside Ocean Terminal. Full details of the updated programme are available on the Trams to Newhaven website.

Councillor Scott Arthur, Transport and Environment Convener, said:It’s great news that this key section of Leith Walk will soon reopen and will start its transition to becoming a vibrant multi-modal transport corridor.

“Not only does it mark a major milestone for the Trams to Newhaven project but I’m sure it will be most welcome to businesses and residents along this part of the route. I’d like to thank all those living and working nearby for their patience throughout the programme of work.

“As the project nears completion, the progress made so far is clear to see. Once finished, it will be transformative for the area and beyond. As well as delivering a low-carbon, high capacity and clean mode of transport to this densely populated part of Edinburgh, it will create improved public spaces, active travel links and support future growth and development.

I do of course recognise that changes to the programme, which are down to issues outwith our control, are likely to affect people and we’ll be working hard to share the latest information and will continue to look at ways in which we can mitigate against some of these delays. To ensure residents are kept safe, I have also asked that parking restrictions are robustly enforced along the route.

“I’d like to thank the Trams to Newhaven project team for all their hard work. Despite the pandemic and global logistics problems, the project is on track to welcome its first passengers in spring 2023 and will be delivered within budget.”

Maria Ortega, SFN Project Director on Edinburgh Trams York Place to Newhaven, said: “We continue to make excellent progress on this project on behalf of our client The City of Edinburgh Council and we are delighted to be reopening this key section of Leith Walk to two-way traffic.

“As contractors we are working hard to ensure that continued progress is made throughout the remaining section of works. Despite the challenges of the pandemic and industry wide issues, we are proud of the progress we have made by working successfully alongside our partners, supply chain and client.

“We look forward to this line being operational in spring 2023.”

Steve Jackson, Project Director, Turner & Townsend said: “As a project we have experienced numerous challenges, as well as industry wide issues, however collaborative working has played a key role to ensure that we have remained on track throughout the life cycle of the project.

“As we enter the final phase of construction works to deliver the Edinburgh Trams to Newhaven line, achievements such as this begin to bring the project together in real life and allow people to see the positive transformational impact this system will have for them.

“I would like to thank all project partners for their efforts to date and we look forward to making continued progress across the route.”

As part of the changes, there is no waiting or stopping between Pilrig Street and Annandale Street, though there is designated loading and parking provision on both the east and west side of Leith Walk.

Logistics hubs to support businesses on Albert Street and Montgomery Street with deliveries and dispatches will also remain on this section of Leith Walk.

MEANWHILE, there’s still no sign of the report into the Edinburgh Trams fiasco. Lord Hardie’s inquiry was set up in 2014 to establish why the Edinburgh Tram project incurred massive delays, cost massively more than originally budgeted and through reductions in scope delivered not a network but a single line, significantly less than promised.

Find out more about Trams to Newhaven, including landscape plans and timelines, online. Further information on bus diversions and timetables is available on the Lothian Buses website.

Next stage for Trams to Newhaven

More traffic disruption inevitable

A new phase of work on the Trams to Newhaven project is set to begin, as the scheme continues to take shape along the route.

Significant progress has been made on several elements of the project, which remains on target for completion in spring 2023 and within the £207.3m budget. More than 60% of track has now been laid (2.8km), 85% of the necessary utility diversions have been carried out and construction work is complete on two new tram stops at McDonald Road and Ocean Terminal.

As part of the next stage of construction the temporary tram stop at York Place, built for the original tram line, will be demolished to allow for the installation of a crossover linking the existing line with the new route.

From 9 February until April the tram from Edinburgh Airport will stop at the West End stop on Shandwick Place. From April, the tram will terminate at St Andrew Square. Details of operational arrangements for this are available on the Edinburgh Trams website.

Construction work on a new, permanent stop at Picardy Place will begin in May. This will come into use when the line to Newhaven opens in 2023.

With construction works on the west side of Leith Walk nearing completion, February will also see changes to traffic management in the area. While traffic will continue to run citybound, from 2 February it will be moved from the east to the west side of the road so that changes to kerb lines, improvements to public realm and the creation of a new carriageway can be carried out on the east side.

This means Pilrig Street and Steads Place can reopen for southbound traffic. There will be some closures to side streets on the east of Leith Walk at certain times, with further details published on the Trams to Newhaven website when these closures are implemented.

Councillor Lesley Macinnes, Transport and Environment Convener, said: “We’re entering a significant phase of the Trams to Newhaven project, as we work to link the old line to the new. We are in the final year of construction for the project which will be followed by a period of testing and commissioning ahead of opening for service in Spring 2023.

“With 60% of track laid and main construction on two of the new tram stops completed, we’re making great progress and it’s exciting to be able to see elements of the new line in place, giving us an idea of how the route will look next year.

“Of course, as is expected of major infrastructure projects of this nature, there is bound to be some disruption, and I’d like to thank all those living and working nearby for their patience.

“We’re working hard to mitigate the impacts and will continue liaising with residents, businesses and public transport providers to keep them up to date.”

Councillor Karen Doran, Transport and Environment Vice Convener, said:  “Delivering the tram line to Newhaven will unlock a large area of the city for housing and economic development, while providing a sustainable, reliable mode of transport to densely populated communities.

“We’re clearly making great strides towards its completion, and we’re making every effort to minimise disruption as part of this process.”

Logistics hubs on Montgomery Street, Albert Street, Dalmeny Street and near the Foot of the Walk will remain open for local businesses as part of the Support for Business package, which also includes a local voucher scheme and a business continuity fund.

As work on a bidirectional cycle lane continues the existing cycle diversion remains in place on either side of Leith Walk. Pedestrian footways and access to shops, hospitality and leisure venues on the east side will be maintained at all times.

The London Road to Crown Street section of the project is estimated to be complete by July 2022, while it is expected that the London Road to York Place section will be finished in September.

EIGHT years on, there’s still no sign of any report from Lord Hardie’s Edinburgh Tram inquiry …

Find out more about Trams to Newhaven online.

Assault in Montgomery Street: Do you know these men?

Police have released a CCTV image of two men they wish to speak to as they may have information which could assist with ongoing enquiries into an assault that occurred around 1.30pm on Monday 2 September, 2020 on Montgomery Street.

One of the men is described as being white and in his late 20s to early 30s. He has short dark hair, stubble and was wearing black casual clothing.

The second man is white, in his mid-20s, 6ft to 6ft 4in tall and of slim build with fair hair. He was wearing a grey jumper, dark bottoms and black body warmer jacket.

Detective Constable Philip Wright of Gayfield CID said: ” As part of the investigation, we are eager to identify the two men in the CCTV footage and would urge them, or anyone who recognises them, to get in touch with us immediately.”

Those with information can contact Police Scotland on 101, quoting incident number 1528 of the 2nd September 2020, or contact Crimestoppers anonymously on 0800 555 111.

Appeal after teenager injured following racial abuse

Police in Edinburgh have released a CCTV image of a man they wish to trace as part of their ongoing enquiries concerning an assault on a teenager.

CCTV Image

The incident took place around 11am on Thursday 25th April in Montgomery Street, near the junction with Hillside Street. Continue reading Appeal after teenager injured following racial abuse