Council gives initial response to scathing Tram Inquiry report

‘serious mistakes were made’ – Council Leader


Council Leader Cammy Day has responded to the publication of the Edinburgh Tram Inquiry. He said: “As a Council, we’ve co-operated fully with Lord Hardie’s Edinburgh Tram Inquiry since its announcement nine years ago and have always maintained that its outcomes will be beneficial in informing investment in similar major transport infrastructure projects, both here in Edinburgh and by other local authorities.

“We’ll consider our response, and any actions required, based on the findings and report back to Transport Committee in November and then our Council meeting in December.

“From a first reading of the report it’s clear that serious mistakes were made and that this had a significant impact on the city. There’s no getting away from the fact that the original project caused a great deal of disruption to residents and businesses, as well as damaging the city’s reputation and on behalf of the Council, I want to apologise for this.

The scathing 959-page report lays the blame for the tram fiasco – years late, millions of £ over budget and delivering only a single line, far less than was promised – at the door of TIE (the council’s tram firm), the council itself and the Scottish Government.

Cammy Day went on: “I won’t, however, apologise for building a tram system, or for our ambition to develop it further.

After all, creating a better connected, environmentally friendly transport system is essential for a modern, successful city and we need to transform the way people move around if we are to achieve our net zero goals.

“Equally, we shouldn’t forget that, in the nine years since the line between Edinburgh Airport and York Place was built, the service has flourished to become a hugely successful transport route for thousands of residents and visitors each day.

“We’ve now launched passenger services on the completed line to Newhaven, the success of which was down to the hard work of the in-house project team and partners, but also thanks to lessons learned from the first project.

“Prior to the announcement of the Inquiry, and towards the closing stages of the first project, we’d already introduced a raft of changes to project management and governance, which also proved crucial to the succesful implementation of the current Trams to Newhaven project.

“In developing the Trams to Newhaven route, clear, timely communication has been key, both between project managers, contractors and elected members but also residents, businesses and other stakeholders. The final business case built on months of extensive consultation on the designs and plans, updating and amending them in response to feedback so that they meet the community’s needs.

“We’ve drawn on the experience of skilled project managers throughout, with a particular focus on securing independent oversight and expert advice at every stage. The establishment of a tram board incorporating independent members, for example, has allowed effective scrutiny, while taking on board the advice of industry experts, such as Professor Bent Flyvbjerg, helped us to take full account of the risks involved.

“We made every effort to minimise disruption and, throughout construction, kept local people, businesses and elected members informed through regular updates, responding to concerns and questions.

“The new route’s already proving to be extremely popular, with passenger numbers doubling in the first few weeks and August clocking in as Edinburgh Trams’ best ever month, with more than 1.2m customer journeys recorded.

“We’re already looking at options for expanding the network further – to the north and south of the city, and potentially also to neighbouring authorities – and it’s encouraging to see this is very much part of the Scottish Government’s plans too.”

Read the full Edinburgh Tram Inquiry report … and weep!

Edinburgh Trams scandal: What’s the delay now? asks Briggs

TRAMS FIASCO REPORT HAS NOW BEEN NINE WEEKS AT PRINTERS

Lothians MSP Miles Briggs said: “It is a perplexing that the Edinburgh Tram Inquiry is still with the printers nine weeks after it was finalised.

“The inquiry was funded by taxpayers money and the public, who have already waited over nine years,  have waited more than long enough to hear the findings.

“I am seeking answers to why the inquiry is on hold at the printers and if a review will be undertaken into the time and costs associated with the delivery of this inquiry.”

AT LAST: Years late and millions overspent, the tram line to Newhaven finally opens

REPORT INTO EDINBURGH’S TRAM FIASCO EXPECTED SOON

The sun shone on Leith yesterday (Wednesday, 7 June) when passenger services on Edinburgh’s new tram line to Newhaven were launched, with the help of the community along the route.

The first paying customers were able to board the service, operated by Edinburgh Trams, between Newhaven and Picardy Place (and onward to Edinburgh Airport) from 12pm.

To celebrate the occasion, a piper accompanied the first tram into the Picardy Place tram stop while members of Edinburgh’s Dance Base performed a specially choreographed ‘tram ballet’ outside St Mary’s Cathedral. The Council Leader then joined local school pupils to officially open the tram for service.

The 2.9 mile, eight stop route, which has been under construction since November 2019, has been delivered on schedule and within the £207.3m budget.

Over recent months rigorous testing to ensure the newly constructed line, software and signals work effectively and safely has included running trams at half and full speed and eventually to timetable, work to integrate signalling and interface with Edinburgh Trams’ control centre and driver familiarisation.

Council Leader Cammy Day said:I’m delighted to be playing a part in this momentous occasion – the launch of tram passenger services between Picardy Place and Newhaven. It’s a real landmark moment for Edinburgh, as we bring this high capacity, sustainable and reliable service to the north of the city.

“I know many will share in my excitement, and optimism for the benefits this development will provide. We’ve already seen vast improvements to spaces along the route and long-term I’m looking forward to the impact it will have on the local economy, which even now we’re starting to see.

“I’d like to take this opportunity to thank all those who live and own businesses along the route. They have shown such patience and resilience throughout this major, complex project and now I hope that they will really gain from the new service.

“This is also a chance to reflect on the hard work of those who have delivered this scheme. Thanks to the project team’s dedication, despite the challenges of recent years, I’m proud to say Trams to Newhaven has been delivered on time and within the £207.3m budget” (!!! See below – Ed.)

Lea Harrison, Edinburgh Trams Managing Director, said:The opening of the route will mark another momentous day for the city, and the entire Edinburgh Trams team stands ready to bring its acclaimed brand of service excellence to tens of thousands of new customers in the communities it serves.

“We’re also looking forward to delivering a real boost for local businesses, providing a convenient transport link between the city centre and some of Edinburgh’s most densely populated neighbourhoods, as well as key locations such as Ocean Terminal and Port of Leith.

“With trams from every seven minutes between 6am and midnight, seven days a week, our expanded tram timetable will help firms large and small to attract new business while helping their employees get to and from work.”

To mark the event, the earliest passengers were able to purchase ‘platinum’ tram tickets from machines at Picardy Place and Newhaven tram stops while Pulse of the Place, a vibrant youth samba band based in north Edinburgh, performed around the Newhaven tram stop.

The Guard of Honour from the High Constabulary of the Port of Leith also stood at Pilrig Street to welcome the tram into the historic Burgh of Leith wearing full parade dress, including top hats, whistles and ceremonial batons.

While the project will open for revenue services on 7 June 2023, outstanding public realm works will continue in some sections.

‘On time and on Budget? Well, no, not quite. The line to Newhaven was part of the original plan for Edinburgh’s tram network. That infamous project became a fiasco, delivering not a network but a SOLITARY LINE – and even that was years late and millions of pounds over budget!

Such was the scale of the shambles of Edinburgh’s tram project that a Public Enquiry was set up under Lord Hardie.

The Inquiry aims to establish why the Edinburgh Tram project incurred delays, cost more than originally budgeted and through reductions in scope delivered significantly less than projected.

The official terms of reference for the Inquiry are to:

  • Inquire into the delivery of the Edinburgh Tram project (‘the project’), from proposals for the project emerging to its completion, including the procurement and contract preparation, its governance, project management and delivery structures, and oversight of the relevant contracts, in order to establish why the project incurred delays, cost considerably more than originally budgeted for and delivered significantly less than was projected through reductions in scope.
  • Examine the consequences of the failure to deliver the project in the time, within the budget and to the extent projected.
  • Review the circumstances surrounding the project as necessary, in order to report to the Scottish Ministers making recommendations as to how major tram and light rail infrastructure projects of a similar nature might avoid such failures in future.

Lord Hardie’s Report into the Edinburgh Trams Project was finally handed over to the publishing company on 26 April and will be with them ‘for several weeks’.  

We should find out soon just where all our missing millions went. Platinum tram tickets indeed – and we’ve certainly payed dearly for them!

Find out more about Trams to Newhaven.

First trams on route to Newhaven

A little piece of local history was made on Monday night (13 March), when the first tram in over 65 years ran down Leith Walk, as the Trams to Newhaven project nears completion.

Ahead of the route opening for service in spring 2023, a period of testing and commissioning is required to ensure the newly constructed line, software and signals work effectively and safely.

On Monday, the first stage of testing began, which involves trams travelling at walking pace along small sections of the route, starting at Picardy Place. This will continue through the week, taking place during the night to minimise traffic disruption.

Once the first stage is completed, the frequency and speed of tram testing will increase, and trams will start running to a timetable. Drivers on the route have carried out significant training in the lead-up to testing, including on a state-of-the-art simulator.

People are still being encouraged to take care and be aware of the presence of trams on the route for the first time over the coming weeks.

Councillor Scott Arthur, Transport and Environment Convener, said: “This is a huge milestone for Trams to Newhaven as we see the first trams on Leith Walk in my lifetime.

“We’re fast approaching the start of passenger services this spring, and that the project is set to be delivered on time and within budget, despite the challenges of recent years, is testament to the hard work of all those involved.

“Bringing the tram to Newhaven will be transformative for the area, and the wider city. As well as boosting the economy and providing sustainable, high-capacity public transport to this densely populated part of Edinburgh, the project has significantly improved the entire route, with new cycle links, spaces to relax and spend time and newly planted trees and shrubs.

“As we enter the final phase of the project, testing and commissioning will make sure the line and infrastructure works safely and efficiently, while also confirming service capacity. Of course, this is the first time there will be trams on Leith Walk and in Leith in recent years so I would urge people to take extra care when in the area.”

Lea Harrison, Managing Director of Edinburgh Trams, said:To see one of our trams running along Leith Walk was a proud moment for us, and this latest milestone in the project will enable us to step up our own preparations for the launch of passenger services to Newhaven.

“This includes real-world driver training on the new section of line following an intense period of familiarisation involving our state-of-the-art tram simulator.”

You could argue that this ‘historic’ event is actually running years late. The line to Newhaven and the Granton Spur were part of the original TIE network plans. The trams fiasco is the subject to a long-running inquiry led by Lord Hardie which is investigating the reasons why ‘the Edinburgh Tram project incurred delays, cost more than originally budgeted and through reductions in scope delivered significantly less than projected.’

The council maintains that the Trams to Newhaven project ‘remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction now complete’. A specific date for when the route will be open for passengers will be announced in due course.

As part of the commissioning process every aspect of the new infrastructure will be thoroughly tested to ensure it meets the required safety standards.

There will be some bus diversions around Leith Walk in place overnight during the week commencing 13 March to allow for the testing. 

The latest information on diversions is available on the Lothian Buses website.

The council warns: ‘Due to industry wide challenges with the availability of materials and skilled labour, impacted by Brexit and the war in Ukraine along with significant demand for labour in the UK and overseas, there are small pockets of public realm works that will now be completed over the coming months.’

Full details of the programme are available on the Trams to Newhaven website.

Maria Ortega, Sacyr Farrans Neopul (SFN), project director on Trams to Newhaven, said: “As contractors on the Trams to Newhaven project, the Sacyr Farrans Neopul JV team are extremely proud to be achieving this huge milestone.  

“We have been working successfully alongside our partners, supply chain and client for over four years to deliver this significant project in Edinburgh, Scotland.

“Despite the challenges of unprecedented times experienced throughout the life cycle of the project, seeing the first tram travelling down the newly completed line as part of the testing and commissioning process will be a memorable moment.

“The testing and commissioning phase will allow the new systems and infrastructure to be integrated into the existing tram network.

“As we reach the final stages of delivering this key piece of infrastructure to the people of the city, we appreciate the public’s continued support during this final technical phase of the project.”

Steven Jackson, Director, Turner & Townsend, said: “As the City of Edinburgh Council’s delivery partner for the Trams to Newhaven project, we’re delighted to have reached this significant milestone with the commencement of the testing and commissioning period, which will see trams travelling the full route.

“Following approval of the project in March 2019, we have worked closely with all members of the project team and third parties through an early contractor involvement period, significant utility diversions, and the install of new infrastructure and systems.

“The complexity of this ambitious project has required the team to tackle and overcome many challenges along the way, but collaboration has been key.

“We look forward to successfully delivering this major transport project in line with the programme set out in the final business case; and the start of the passenger services this Spring.”

Find out more about Trams to Newhaven, including landscape plans and timelines.

Hallelujah! Key section of Leith Walk to reopen on Monday

BUT TRAFFIC CHAOS IS FAR FROM OVER

Leith Walk will reopen to two-way traffic between Pilrig Street and London Road from Monday (18 July), marking a key milestone for the Trams to Newhaven project.

The main construction works between Montgomery Street/Annandale Street and Pilrig Street are now complete and fencing will be removed from outside businesses and homes.

The project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction anticipated to be complete by the end of 2022 ahead of a testing and commissioning period.

Progress to date includes:

  • Almost 3,900 metres of track laid, 84% of the total
  • Main construction works completed on three out of the eight new tram stops with works progressing well at the Balfour Street, Foot of the Walk and Newhaven stops
  • Over 4,000 metres of communications ducting installed (87% of the total) serving the tram and future communication requirements in the area
  • More than 4,000 metres of drainage installed (89% of the total)
  • Over 60,000 deliveries from the logistic hubs to local businesses
  • Almost 24,500 itison vouchers sold, generating over £240,000 potential spend in participating businesses on the route.
  • Over £175,000 spend on open for business campaigns
  • Main construction works complete on several sections, including Ocean Terminal to Rennie’s Isle and between Tower Street and Constitution Place and Tower Street and Baltic Street

However, the programme for some specific sections of the route has changed due to industry wide challenges with the availability of materials and skilled labour, as well as other issues including complex utility conflicts.

As a result, some stretches are scheduled to take longer than originally planned, including Melrose Drive and outside Ocean Terminal. Full details of the updated programme are available on the Trams to Newhaven website.

Councillor Scott Arthur, Transport and Environment Convener, said:It’s great news that this key section of Leith Walk will soon reopen and will start its transition to becoming a vibrant multi-modal transport corridor.

“Not only does it mark a major milestone for the Trams to Newhaven project but I’m sure it will be most welcome to businesses and residents along this part of the route. I’d like to thank all those living and working nearby for their patience throughout the programme of work.

“As the project nears completion, the progress made so far is clear to see. Once finished, it will be transformative for the area and beyond. As well as delivering a low-carbon, high capacity and clean mode of transport to this densely populated part of Edinburgh, it will create improved public spaces, active travel links and support future growth and development.

I do of course recognise that changes to the programme, which are down to issues outwith our control, are likely to affect people and we’ll be working hard to share the latest information and will continue to look at ways in which we can mitigate against some of these delays. To ensure residents are kept safe, I have also asked that parking restrictions are robustly enforced along the route.

“I’d like to thank the Trams to Newhaven project team for all their hard work. Despite the pandemic and global logistics problems, the project is on track to welcome its first passengers in spring 2023 and will be delivered within budget.”

Maria Ortega, SFN Project Director on Edinburgh Trams York Place to Newhaven, said: “We continue to make excellent progress on this project on behalf of our client The City of Edinburgh Council and we are delighted to be reopening this key section of Leith Walk to two-way traffic.

“As contractors we are working hard to ensure that continued progress is made throughout the remaining section of works. Despite the challenges of the pandemic and industry wide issues, we are proud of the progress we have made by working successfully alongside our partners, supply chain and client.

“We look forward to this line being operational in spring 2023.”

Steve Jackson, Project Director, Turner & Townsend said: “As a project we have experienced numerous challenges, as well as industry wide issues, however collaborative working has played a key role to ensure that we have remained on track throughout the life cycle of the project.

“As we enter the final phase of construction works to deliver the Edinburgh Trams to Newhaven line, achievements such as this begin to bring the project together in real life and allow people to see the positive transformational impact this system will have for them.

“I would like to thank all project partners for their efforts to date and we look forward to making continued progress across the route.”

As part of the changes, there is no waiting or stopping between Pilrig Street and Annandale Street, though there is designated loading and parking provision on both the east and west side of Leith Walk.

Logistics hubs to support businesses on Albert Street and Montgomery Street with deliveries and dispatches will also remain on this section of Leith Walk.

MEANWHILE, there’s still no sign of the report into the Edinburgh Trams fiasco. Lord Hardie’s inquiry was set up in 2014 to establish why the Edinburgh Tram project incurred massive delays, cost massively more than originally budgeted and through reductions in scope delivered not a network but a single line, significantly less than promised.

Find out more about Trams to Newhaven, including landscape plans and timelines, online. Further information on bus diversions and timetables is available on the Lothian Buses website.

Next stage for Trams to Newhaven

More traffic disruption inevitable

A new phase of work on the Trams to Newhaven project is set to begin, as the scheme continues to take shape along the route.

Significant progress has been made on several elements of the project, which remains on target for completion in spring 2023 and within the £207.3m budget. More than 60% of track has now been laid (2.8km), 85% of the necessary utility diversions have been carried out and construction work is complete on two new tram stops at McDonald Road and Ocean Terminal.

As part of the next stage of construction the temporary tram stop at York Place, built for the original tram line, will be demolished to allow for the installation of a crossover linking the existing line with the new route.

From 9 February until April the tram from Edinburgh Airport will stop at the West End stop on Shandwick Place. From April, the tram will terminate at St Andrew Square. Details of operational arrangements for this are available on the Edinburgh Trams website.

Construction work on a new, permanent stop at Picardy Place will begin in May. This will come into use when the line to Newhaven opens in 2023.

With construction works on the west side of Leith Walk nearing completion, February will also see changes to traffic management in the area. While traffic will continue to run citybound, from 2 February it will be moved from the east to the west side of the road so that changes to kerb lines, improvements to public realm and the creation of a new carriageway can be carried out on the east side.

This means Pilrig Street and Steads Place can reopen for southbound traffic. There will be some closures to side streets on the east of Leith Walk at certain times, with further details published on the Trams to Newhaven website when these closures are implemented.

Councillor Lesley Macinnes, Transport and Environment Convener, said: “We’re entering a significant phase of the Trams to Newhaven project, as we work to link the old line to the new. We are in the final year of construction for the project which will be followed by a period of testing and commissioning ahead of opening for service in Spring 2023.

“With 60% of track laid and main construction on two of the new tram stops completed, we’re making great progress and it’s exciting to be able to see elements of the new line in place, giving us an idea of how the route will look next year.

“Of course, as is expected of major infrastructure projects of this nature, there is bound to be some disruption, and I’d like to thank all those living and working nearby for their patience.

“We’re working hard to mitigate the impacts and will continue liaising with residents, businesses and public transport providers to keep them up to date.”

Councillor Karen Doran, Transport and Environment Vice Convener, said:  “Delivering the tram line to Newhaven will unlock a large area of the city for housing and economic development, while providing a sustainable, reliable mode of transport to densely populated communities.

“We’re clearly making great strides towards its completion, and we’re making every effort to minimise disruption as part of this process.”

Logistics hubs on Montgomery Street, Albert Street, Dalmeny Street and near the Foot of the Walk will remain open for local businesses as part of the Support for Business package, which also includes a local voucher scheme and a business continuity fund.

As work on a bidirectional cycle lane continues the existing cycle diversion remains in place on either side of Leith Walk. Pedestrian footways and access to shops, hospitality and leisure venues on the east side will be maintained at all times.

The London Road to Crown Street section of the project is estimated to be complete by July 2022, while it is expected that the London Road to York Place section will be finished in September.

EIGHT years on, there’s still no sign of any report from Lord Hardie’s Edinburgh Tram inquiry …

Find out more about Trams to Newhaven online.

Rabbie’s back on Bernard Street!

Leith’s iconic Burns statue returned to its home on Bernard Street as Scotland prepared to celebrate the national bard.

The 19th century bronze sculpture was put into storage in December 2019 to make way for Trams to Newhaven construction. It has since undergone specialist conservation work before its reinstatement at Bernard Street’s junction with Constitution Street.

Yesterday, on the morning of Burns Night (Tuesday, 25 January), Council leaders, tram project officers and contractors were joined by conservationists and former Edinburgh Makar Alan Spence to unveil the monument.

They also marked the placement of a new time capsule underneath the statue, alongside an original capsule discovered in 2019, which contained relics from both the late 19th century and the 1960s.

Councillor Lesley Macinnes, Transport and Environment Convener, said: “I’m delighted to see this much-loved Robert Burns statue returned to its home in Leith – and spruced up thanks to specialist conservation work – just in time for Burns night.

It’s fantastic that so many members of the community have been able to contribute to the new time capsule placed underneath the statue. Thanks to their input we’ll be able to share an insight into Leith today with future generations, just like our 19th century forebears did when they buried the original time capsule.

Councillor Karen Doran, Transport and Environment Vice Convener, said: “What better way to celebrate Scotland’s national bard than the unveiling of this newly-restored statue?

Its return also marks progress being made on the Trams to Newhaven project, as the area begins to take shape. I’m excited to see what the coming months will bring as ongoing improvements are delivered.”

In November last year the Trams to Newhaven project reached its two-year point and, despite challenges posed by the Covid pandemic, including a 13-week site shutdown, remains on track for opening for revenue service in Spring 2023.

The next main phase of construction between Coatfield Lane and Queen Charlotte Street began this week, while it is hoped the current stage of work on Picardy Place, which has resulted in some changes to traffic management, will be complete by spring. The entire section from York Place to London Road is expected to be completed in Autumn 2022.

On Tuesday, Alan Spence read out a specially written poem, which has been added to the 2021 time capsule created for the statue’s reinstatement. The capsule also contains poems and stories by Victoria Primary School pupils, a letter from the Edinburgh Burns Club, coins from 2021 and a face mask, amongst other artefacts.

This has been placed in a purpose-carved socket in the plinth underneath the monument along with the original time capsule, which originates from when the statue was first erected in 1898.

This was opened when the statue was moved in December 2019 and its contents include newspapers, coins and a letter from the Leith Burns Club. From 1961, there were newspapers and a letter from the people who had opened the original time capsule.

Meanwhile, Lord Hardie’s Edinburgh Tram Inquiry trundles on … EIGHT YEARS AND COUNTING I wonder what Rabbie would have said about that!

Find out more about the Trams to Newhaven project online.

Business case for Trams to Newhaven ‘remains on track’

An update to the final business case for the Trams to Newhaven project, which reflects the impact of the ongoing COVID-19 pandemic, concludes that the economic case for the scheme remains positive.

The review aims to assess the impact any changes in public transport demand as a result of the crisis could have on the economic and financial case, first approved in March 2019. On Thursday (12 November 2020) members of the Transport and Environment Committee will be asked to consider the updated final business case (FBC) and to approve continuing with the construction of the project.

The Council’s economic advisers, have developed a series of possible scenarios to stress-test the findings in the original FBC. These range from a return to business as usual to a permanent reduction in demand, taking into account short-term COVID-19 impacts and views on future growth. In each of the scenarios, modelling suggests that the economic case for the project remains, with a benefit-to-cost ratio of above one.

Financial assessment has found that the project can still be delivered within the budgeted £207.3m and that, in all but one of the scenarios, the impact on Council reserves if the project is cancelled would be greater than continuing construction. While it is possible there could be a future call on Council reserves to support financing costs as a result of COVID-19, in each scenario the scheme will finance itself, albeit in different timeframes.

The refreshed FBC also highlights that the completion will play a key role in the future growth and development of the city. Delivering the tram line to Leith will unlock a large area of the city for housing and economic development, while providing a low-carbon, clean mode of transport to densely populated communities.

Transport and Environment Convener Councillor Lesley Macinnes said: “It’s clear that the events of this year have had an unprecedented impact on the way we travel and that we’ll continue to feel the effects for the foreseeable future. In light of this, it’s essential that we assess the potential economic and financial impacts on such a significant transport infrastructure scheme.

“I’m pleased that the economic and financial cases for Trams to Newhaven hold up despite the ongoing pressures resulting from COVID-19. The delivery of this project is essential for the Capital’s green recovery, providing sustainable, low-carbon travel to one of the city’s most densely populated areas. We now have reason to be cautiously optimistic as we progress with construction.”

Transport and Environment Vice Convener Councillor Karen Doran said: “The Trams to Newhaven project is exactly the kind of investment we need post-COVID-19 to ensure Edinburgh is a thriving, forward-looking place for people to live and work in and to deliver much needed housing, jobs and investment into north Edinburgh.”

Work on the Trams to Newhaven project was instructed to stop on 25 March following guidance from the First Minister on COVID-19 and recommenced in June. While the site shutdown incurred costs, these have been covered by the overall budget and delays have been mitigated.

An updated programme shows that the project is still working towards Spring 2023 for completion and is forecast to be delivered within the agreed budget.

Over recent months, Edinburgh has experienced a significant drop in demand for public transport, with long-term consequences expected including a decline in income to the tram service.

The review of the FBC takes this into account, with even the most optimistic of scenarios projecting that passenger numbers won’t return to pre-COVID levels until the mid-2020s. Finally, the review of the FBC acknowledges the impact of COVID 19 on Lothian Buses and does not rely on any further payment of the extraordinary dividend which was anticipated in the original FBC.

Since March 2019 several local and national strategies have emerged to further support the introduction of high capacity, high quality public transport in the city. While Scotland’s National Transport Strategy 2 (NTS2) envisions ‘sustainable, inclusive, safe and accessible transport’, Edinburgh’s draft City Mobility Plan strives for a greener, safer and connected transport system.

The tram will support the delivery of transport policies such as City Centre Transformation, which proposes a series of interventions to provide a more liveable, people-friendly city centre and requires a mode shift to public transport to help deliver a 10-15% reduction in city centre car traffic in the medium term and a 25-30% reduction in the longer term.

Read the full report, Trams to Newhaven – COVID-19 Final Business Case Refresh, online. 

Watch Transport and Environment Committee live via webcast from 10am on Thursday, 12 November.

While the city council pushes ahead with the trams project, the Inquiry into the Edinburgh Tram project also continues – albeit at a snail’s pace.

The inquiry aims to establish why the original Edinburgh Tram project incurred delays, cost more than originally budgeted and through reductions in scope delivered significantly less than projected.

The inquiry, under Lord Hardie, was set up in June 2014 but is yet to report any findings.

Back in June a spokesperson for the Edinburgh Tram Inquiry told the BBC: “The findings of the inquiry into why the Edinburgh Trams project incurred delays, cost more than originally budgeted and delivered significantly less than planned will be made available at the earliest opportunity.

“Lord Hardie’s remit is to conduct a robust inquiry and it will take as long as is necessary to get the answers required to fulfil the terms of reference.

“We continue to make good progress, including managing more than three million documents on the inquiry’s evidence database for handover to National Records of Scotland.

“A relevant set is also being prepared to be made available on the inquiry’s website to accompany the published report at the appropriate time.”

A scathing review by Audit Scotland in February 2011 noted the original tram project had been undermined by poor planning, cost underestimates, contract disputes and a lack of clear leadership by the council – a lengthy catalogue of calamities which has cost taxpayers £ millions.

Carry On Tramworks!

Construction site preparation works for Edinburgh’s Trams to Newhaven project will restart tomorrow (Monday, 1 June) in line with the Scottish Government’s Phase 1 pre-start site preparation.

Work on the project was stopped at the end of March to comply with Scottish Government guidance and to protect the safety of workers and residents during the coronavirus outbreak.

Following the First Minister’s announcement on 21 May of a phased return for construction sites, plans have been drawn up in line with Scottish Government safety guidelines and industry best practice to ensure the safety of workers and the public. At a briefing on Thursday the First Minister confirmed that site preparation could begin.

In advance of the main work beginning, works to prepare construction sites and project offices will include the introduction of infection control stations, additional water stations and toilet facilities for workers within the site and in the project office, and ensuring all office workspaces and facilities are set up appropriately.

Other works on site will include the removal of the protective in-fill material that was used to ensure the work site remained safe and protected during the shutdown.

Measures to protect workers’ health will include daily briefings, continuous on-site inspections and health and safety ‘ambassadors’. The numbers of workers on-site will be kept to a minimum and the majority of project office staff will continue to work from home.

Council Leader Adam McVey said: “Following updated advice from the Scottish Government, we will be carrying out site preparatory works on the Trams to Newhaven project from Monday, 1 June.

“The safety of workers and the public is of utmost importance during this time and all works will be undertaken in compliance with the Government’s guidance on construction working and to allow physical distancing.

“The tram team have put in an enormous amount of hard work with our contractors to take us through this challenging period and it will take some time to fully remobilise sites. The implications of COVID-19 are unlikely to be understood for some time but we continue to work to mitigate the impact as we progress with the project.”

Depute Leader Cammy Day said: “The Trams to Newhaven project is being delivered for the future of our city and is one of a number of schemes that are crucial to the sustainable, long-term development of the city, helping decarbonise the way we travel.

It is exactly the kind of investment we need post-COVID-19 to ensure Edinburgh is a thriving, forward-looking place for people to live and work in and will help to encourage much needed affordable housing, jobs and investment into North Edinburgh.”

Alejandro Mendoza Monfort, Director of Sacyr Farrans Neopul, the main infrastructure contractor, said: “SFN are delighted that we can restart our works on the Trams to Newhaven project. We understand the importance that this project will have for Edinburgh’s future and are committed to ensuring that we continue to mitigate the impact of Coronavirus 19. During this pause period, concentrated efforts have continued behind the scenes to develop and test a series of robust systems and procedures, whilst ensuring the highest level of health, safety and wellbeing can be provided.

“We have used this time to adapt to our new working world and developed new operating procedures that provide information, guidance and site-specific measures that will be implemented when conducting works to mitigate the impact, so far as reasonably practicable, of the virus.”

Mike Thomson, Director of Morrison Utility Services, said: “We are very pleased to be able to begin to prepare to restart this important project for Edinburgh.

” The safety of colleagues and the public is paramount and MUS has been working closely with the City of Edinburgh Council and SFN to ensure that our working practices are fully compliant with the guidance given by the Scottish Government, while also looking at ways in which we can mitigate the impact of the recent enforced shutdown.”

Once the construction industry is given the approval to move to Phase 2, works on the existing sites will recommence and the Leith Walk construction site will be established as planned prior to site shutdown.

Any commencement of main works will be subject to the Scottish Government giving approval to move to Phase 2 of their construction guidelines which states: ‘soft start to site works (only where physical distancing can be maintained)’.

The project team has been working on plans to mitigate the impact of the enforced shutdown as a result of COVID-19 on the programme and budget. Despite the current circumstances, the project continues to operate within its £207.3m budget. The project is paid for by borrowing monies that are repaid over a 30-year period through future revenues from customers.

While work on the latest phase of the Edinburgh tram project gets back underway, SIX YEARS ON there’s still no sign of a long-awaited report on the shambolic first phase.

The Edinburgh Tram Inquiry was commissioned by Scottish Ministers and in June 2014, the Inquiry was formally announced by then First Minister Alex Salmond. The Inquiry is chaired by Lord Hardie.

The Edinburgh Tram Inquiry aims to establish why the Edinburgh Tram project incurred delays, cost more than originally budgeted and through reductions in scope delivered significantly less than projected.

The official terms of reference for the Inquiry are to:

  • Inquire into the delivery of the Edinburgh Tram project (‘the project’), from proposals for the project emerging to its completion, including the procurement and contract preparation, its governance, project management and delivery structures, and oversight of the relevant contracts, in order to establish why the project incurred delays, cost considerably more than originally budgeted for and delivered significantly less than was projected through reductions in scope.
  • Examine the consequences of the failure to deliver the project in the time, within the budget and to the extent projected.
  • Review the circumstances surrounding the project as necessary, in order to report to the Scottish Ministers making recommendations as to how major tram and light rail infrastructure projects of a similar nature might avoid such failures in future.

 

 

Capital Coalition set to vote through £207 million tram extension

Edinburgh’s ruling SNP – Labour Capital Coalition is set to give the green light to a controversial £207 million tram line extension today – despite an ongoing  inquiry into the capital’s original trams debacle. Continue reading Capital Coalition set to vote through £207 million tram extension