Ferry Road set for seven months of traffic misery

Persevere?

Traffic at the east end of Ferry Road will be severely disrupted for up to 28 weeks when Scottish Gas Networks begins major work to replace mains pipes at the end of this month. The company says the upgrade to the network is essential, but commuters and local residents look set for seven miserable months of road closures, parking restrictions, diversions and temporary traffic lights.

In a statement, Scottish Gas Networks said: ‘The existing metal gas mains and services in the vicinity of Ferry Road, need to be replaced with modern plastic polyethylene (PE) pipe to ensure a continued safe and reliable gas supply to the local area. We will be renewing 1.75km of gas mains.

This essential work forms part of our ongoing mains replacement programme developed with the Health and Safety Executive. Work will last for approximately 28 weeks and will be carried out by May Gurney on our behalf.

We have been working closely with the City of Edinburgh Council, Lothian and Borders Police and Lothian Buses to plan this project and minimise disruption as much as possible. We will continue to work with these organisations and local residents throughout the course of the project.

Works will begin on Ferry Road, at its junction with Madeira Street and will continue westbound towards Craighall   Road. The works will take place in four phases during which time there will be some temporary traffic lights in operation.

Phase 1 works will be between the junction of Ferry Road with Madeira Street and the junction of Ferry Road with Newhaven Road. This phase will last for approximately six – eight weeks.

During Phase 2 we will be working between the junction of Ferry Road with Newhaven Road and Bonar Place. This will take approximately 10 weeks.

Phase 3 will last approximately four weeks. Works will be on Newhaven Road, from the junction with Ferry Road to the junction with Pitt Street.

Phase 4 will also take place on Newhaven Road, between the junction with Bonnington Avenue and the junction with Stewartfield. During this phase there will also be some works on West Bowling Green Street. The phase will last for approximately six weeks.

Works will be suspended from Friday 21 December for the festive period. They will recommence on Monday 7 January.

To allow for the manoeuvre of heavy plant equipment and to ensure everyone’s safety there will be some parking restrictions in place during the works, as well as some local road closures. Local diversions will be in place where necessary.

All local shops and businesses will be open as usual. Pedestrian access will be maintained at all times and access for deliveries to businesses will be maintained where possible.’

While the company plans to mitigate problems for commuters, traders and residents, the scale of the work is going to have a major impact on Ferry Road and adjacent neighbourhoods.

Scotland Gas Networks’ Team Manager, Simon Kennedy said: “All our works are carried out in close consultation with the local Council and we will do everything we can to minimise disruption. We understand that people get frustrated by roadworks and thank them for their patience while we carry out these essential works.  The new plastic pipe has a minimum lifespan of 80 years. This means that when the work is complete, local residents will continue to enjoy the benefits of a safe and reliable gas supply for years to come.”

More information is available at www.sgn.co.uk

 

 